1. Job size

Compacted, not loose depth behind the screed.

2. Material

Fills in from the material. A rule of thumb, not a spec: type your plant's or supplier's number over it.

5–10% is typical. Confirm against your plant tickets.

3. Cost & trucking (optional)

Example: plug in your own number.

Payload depends on the truck and your state's weight limits. Use your own number.

Tons needed, with waste

Enter the area and thickness above to see tons.

How this is calculated
  1. tons = sq ft × inches ÷ 12 × density ÷ 2000 (sq ft × thickness in feet = cubic feet; × lb per cubic foot = pounds; ÷ 2,000 = tons). At 145 lb/ft³ that's sq ft × inches × 145 ÷ 24,000.
  2. tons with waste = tons × (1 + waste%)
  3. cubic yards = sq ft × inches ÷ 12 ÷ 27 (compacted, in place, before waste)
  4. truckloads = tons with waste ÷ tons per load, rounded up to whole loads
  5. material cost = tons with waste × price per ton

Tons are rounded to the hundredth, the same way a ton line on a estimate rounds them, so this page and your estimates give the same number. Densities are rules of thumb: confirm against your plant tickets.

Send this as a real estimate to your customer

turns a bid into a professional estimate your customer can approve from their phone.

Start free for 14 days, no card

How the asphalt tonnage formula works

Hot mix is sold by the ton, but you measure the job in square feet and inches. The calculator converts one to the other in three steps:

  1. Volume: square feet × thickness in feet (inches ÷ 12) = cubic feet.
  2. Weight: cubic feet × density (lb per cubic foot) = pounds.
  3. Tons: pounds ÷ 2,000.

Put together:

tons = sq ft × thickness (in) × density (lb/ft³) ÷ 24,000

The 24,000 is just 12 inches per foot × 2,000 lb per ton. At the default density of 145 lb/ft³, that's:

tons = sq ft × inches × 145 ÷ 24,000

If you measure in square yards

Multiply square yards by 9 to get square feet, or use the per-yard shortcut. At 145 lb/ft³, one square yard one inch thick weighs about 109 lb (0.054 tons), so:

tons ≈ sq yd × inches × 0.0544

About the 145 lb/ft³ density

145 lb/ft³ is a rule of thumb for compacted hot-mix asphalt, not a spec. The real number depends on the mix: aggregate type, gradation, binder content and how well it's compacted. Two plants' “surface mix” won't weigh the same.

So:

Add waste: how much and why

The formula gives you the asphalt that ends up compacted in place at exactly the thickness you entered. Real jobs use more:

A common allowance is 5–10% waste. Use the low end on a clean overlay of a large, even lot, and the high end on small jobs, patches and anything with a lot of handwork. Your plant tickets will tell you where your crew actually lands.

Worked examples

Examples only. Plug in your own measurements, density and waste.

Residential driveway

12 ft × 50 ft = 600 sq ft at 2 in compacted
600 × 2 × 145 ÷ 24,000 = 7.25 tons
+7% waste = 7.76 → order 8 tons

Larger driveway or small lot

1,500 sq ft at 3 in
1,500 × 3 × 145 ÷ 24,000 = 27.19 tons
+10% waste = 29.9 tons

Parking lot overlay

20,000 sq ft at 1.5 in
20,000 × 1.5 × 145 ÷ 24,000 = 181.25 tons
+5% waste = 190.3 tons

Turning tons into truckloads

Divide total tons by the legal payload of the trucks hauling it, and round up. Payload depends on the truck and your state's weight limits, so use your own number.

What about base, gravel and sand?

The formula is the same. Only the density changes. Base, gravel, decomposed granite and sand all weigh different amounts per cubic foot, and the number changes with moisture and compaction. Get the density from your supplier, put it in the density box, and the math holds.

Common mistakes

Do this math inside your estimates

In , any estimate line billed by the ton does this calculation for you. Enter the area and lift thickness and the tons fill in. Pick hot mix, flex base, gravel, decomposed granite or sand, and each comes with a rule-of-thumb density you can check against your supplier. You can type over the tons whenever your tickets say otherwise.

Even faster: trace the lot on aerial imagery with Measure (Crew plan and up). You get square feet and an estimated tonnage for each shape, and Use in New Estimate turns it into a priced bid you can text to the customer.

See pricing, or start free, 14 days, no card →

Doing maintenance work too? Try the sealcoating calculator.

Related: how to bid sealcoating jobs, sealcoating software and asphalt paving estimating software.

FAQ

How many tons of asphalt do I need?

Multiply square feet × compacted thickness in inches × 145, then divide by 24,000. Add 5–10% for waste. Example: 600 sq ft at 2 in = 7.25 tons, about 7.8 with 7% waste.

How much does a ton of asphalt cover?

At 145 lb/ft³, one ton covers about 166 sq ft at 1 in compacted, 83 sq ft at 2 in, or 55 sq ft at 3 in. Your mix's real density will move those numbers.

How many tons of asphalt per square yard?

About 0.054 tons (roughly 109 lb) per square yard per inch of compacted thickness at 145 lb/ft³. Multiply by your thickness in inches.

What density should I use for hot-mix asphalt?

145 lb/ft³ is a common rule of thumb for compacted hot mix. Confirm it against your plant's tickets or ask the plant for the unit weight of your mix.

How much waste should I add for asphalt?

5–10% is a common allowance. Use more on small, hand-worked jobs and patches, and less on large, even overlays. Track your tickets to find your crew's real number.

Is the thickness loose or compacted?

Compacted. If you're thinking in loose depth behind the paver, the estimate will come up short.